Edgewater Paving Update – 6/13/2016

IMG_1527

Update on the City of Edgewater paving projects from Community Services Director Dan Maples:

Thanks for everyone’s cooperation on this project. I think we all look forward to the day everything is completed!

Well every time I post a schedule, it seems to be changed the next day, but I will try. Most of the reasons for change has been issues that we find after starting work in an area. Here is what we are hearing for a schedule for next week.

Completed Streets:
2500 Block of Gray St.
2500, 2400, 2200 & 2000 Blocks Fenton St.
2500, 2400, 2200 & 2000 Blocks of Depew St.
2500 Block of Chase St. (small South Section to complete)
2500 & 2200 Blocks of Benton St.
2500, 2400 & 2000 Blocks of Ames St.
5300 Block of 22nd Ave.
5400 Block of 24th Ave.

Currently working on:
2200 & 2400 Block of Gray St. (should have first lift of asphalt done today)
5900 – 5700 Blocks of 24th Ave. – Milling today

Next Weeks Schedule:

Saturday, June 11th
5200 – 5900 Blocks of 25th Ave. – Milling (Before 11am)
5900-5700 Blocks of 24th Ave. – First Lift

Monday, June 13th
2200 & 2400 Gray St. – Final Lift
5200 – 5900 Blocks of 24th Ave. – Final Lift
2500, 2400 & 2200 Blocks of Eaton St. – Milling/ First Lift

Tuesday, June 14th
2500, 2400 & 2200 Blocks of Eaton St. – Milling/ First Lift

Wednesday, June 15th
2500, 2400 & 2200 Blocks of Eaton St. – First Lift
2400 Benton St. – Milling
2200 Block Ames St. – Milling

Thursday, June 16th
2400 Benton St. – First Lift
2200 Block Ames St. – First Lift
5200 Block of Ames St. – Milling

Friday, June 17th
2400 Benton St. – Final Lift
2200 Block Ames St. – Final Lift
5200 Block of Ames St. – First Lift

We have put a few streets on hold due to some issues:
2400 Block of Chase St. – Need to add a storm sewer line
2000 Block of Eaton St. – Sub-grade needs to dry out.
2000 Block of Gray St. – Sub-grade needs to dry out.

Our contractor is confident that we will be able to complete our work in early July. Thanks again for everyone’s patience. If you need any further information please feel free to call 720-763-3012.

Dan Maples
Community Services Director
720-763-3012

Be the first to comment on "Edgewater Paving Update – 6/13/2016"

Leave a comment

Your email address will not be published.




This site uses Akismet to reduce spam. Learn how your comment data is processed.

Translate »