Edgewater Street Paving Update – 6/17/2016

Edgewater street paving update from Community Services Director Dan Maples:

Another crazy week is finishing up in Edgewater with the paving crews. I know this week was most likely the busiest week for paving yet. Again another big thanks to everyone’s patience and cooperation in getting this project completed. Below is the schedule we are looking at for next week.

Completed Streets:
2200, 2400 & 2500 Block of Gray St.
2500, 2400, 2200 & 2000 Blocks Fenton St.
2500, 2400, 2200 & 2000 Blocks of Depew St.
2500 Block of Chase St. (small South Section to complete)
2500 & 2200 Blocks of Benton St.
2500, 2400 & 2000 Blocks of Ames St.
5300 Block of 22nd Ave.
5200 – 5600 Blocks of 24th Ave.
5200 – 5900 Blocks of 25th Ave.
2200, 2400 & 2500 Blocks of Eaton St.

Monday, June 20th
2000 Block of Eaton St. – Final Lift
5200 Block of 22nd Ave. – Final Lift
2200 Block of Ames St. – Final Lift

Tuesday, June 21st
2400 Block of Benton St. – Final Lift
5900 Block of Harlan St. – Final Lift
2400 Block of Chase St. – First & Final Lift

Wednesday, June 22 – Friday June 24
Project clean up

We have put one street on hold due to some issues:
2000 Block of Gray St. – Sub-grade needs to dry out.

Thanks again for everyone’s patience. If you need any further information please feel free to call 720-763-3012

Dan Maples
Community Services Director

Be the first to comment on "Edgewater Street Paving Update – 6/17/2016"

Leave a comment

Your email address will not be published.




This site uses Akismet to reduce spam. Learn how your comment data is processed.

Translate »