From Edgewater Community Services Director Dan Maples:
The City of Edgewater will be working with a contractor, Martin Marietta, to mill and pave streets in Edgewater west of Harlan St. and 26th Ave. starting in late September. Below is an initial schedule for paving but will be dictated by weather and/or unexpected project discoveries.
26th Ave. Wadsworth Blvd. – Pierce St. September 22 – October 15
26th Ave. Pierce St. – Sheridan Blvd. September 28 – October 15
Edgewater Residential Streets (listed below): October 12 – October 30
Below is a list of the residential streets included in the 2015 asphalt project.
24th Ave.: Pierce St. – Harlan St. Mill & Overlay
25th Ave.: Marshall St. – Harlan St. Mill & Overlay
22nd Ave.: Newland St. – Harlan St. Mill & Overlay
Otis Crt.: 24th Ave – 25th Ave. Ln. Mill & Overlay
Newland St.: 24th Ave – 25th Ave. Ln. Mill & Overlay
Newland St.: 2000 Block Mill & Overlay
Marshall St.: 2000 Block Street Rebuild
Marshall St.: 24th Ave – 25th Ave. Ln. Mill & Overlay
Lamar St.: 2200, 2400 & 2500 Block Mill & Overlay
Kendall St.: 2000, 2200, 2400, & 2500 Block Mill & Overlay
Jay St.: 2000, 2200, 2400 & 2500 Block Mill & Overlay
Ingalls St.: 2000, 2200, 2400 & 2500 Block Mill & Overlay
We anticipate additional paving for 2016 on the east side of Harlan St., as well as north and south sides of the City. We thank you for your patience through this project and if you have any questions or concerns regarding this project, please feel free to call (720) 763-3012.