In November 2018, Jeffco voters passed Jeffco Public Schools’ ballot questions 5A and 5B. The passage of 5B dedicated $567 million in one-time funds for construction in the school district. Each of the three Edgewater schools (Edgewater Elementary, Lumberg Elementary and Jefferson Junior/Senior High) were slated for additions, remodeling of the building interior and other improvements.
Schools across the district are at different stages of the design and build process, so we reached out to Jeffco Public Schools to get an update on improvements to Edgewater schools.
Below are the preliminary projects and timing for start and completion from Jeffco Public Schools bond construction staff. The specifics could change based on pricing.
Lumberg Elementary
Major improvements: Addition and Remodel – 4 Classroom addition and New Music Room off of gym. Remodel to include secure entry, art room, library, new preschool classrooms, updated kindergarten classrooms, additional office space and new preschool playground. Replacement of mechanical systems & removal of the temps with site updates.
Planned construction start: Fall 2020
Planned construction completion: Fall 2021
Jefferson Junior/Senior High School
Major improvements: Addition and Remodel – Addition to include new Aux Gym with locker rooms, new office and counseling wing with secure front entrance. Remodel to include four general classrooms, drama room and new FACS classroom.
Planned construction start: Fall 2020
Planned construction completion: Fall 2021
Edgewater Elementary School
Major improvements: you can find the improvements coming to Edgewater through this link: https://www.jeffcopublicschools.org/services/facilities/jeffcobuilds/JB_Artics/jefferson_articulation
Planned construction start: Sept 2021 (this is the start of design, TBD on actual construction)
Planned construction completion: Oct. 2023
Joel has been a resident of Edgewater, Colorado with his family since 2012. He is the Executive Director of local education nonprofit Edgewater Collective and Editor of the Edgewater Echo.